I. Project Overview
Ningbo Huatai Shengfu Polymer Materials Co., Ltd. was established on December 12, 2012, and is located at No. 18 West Huan Dao Road, Daxie Development Zone, Ningbo. The company plans to implement a 700,000-ton-per-year light hydrocarbon utilization project on the Jiaomen plot in the Daxie Development Zone (Daxie North Petrochemical Industrial Park). This project received approval and was officially approved in September 2017 under Document No. Yong Fa Gai Bei [2017]40. Construction is scheduled to commence in 2018 and be completed in 2019. Upon completion, the project is expected to have an installed capacity of 2 × 63,000 kVA, with a normal electricity load of 54,100 kW and a peak electricity load of 56,600 kW.
This project involves the construction of one new 110-kV dedicated substation, with two 110-kV incoming feeders, both configured as single-bus sectionalized schemes. The main transformers are all 2 × 63 MVA units, employing 110/35-kV dual-winding transformers. The 110-kV customer substation of Ningbo Huatai Shengfu Polymer Materials Co., Ltd. will be connected to the 220-kV Leng’ao Substation via two newly constructed 110-kV transmission lines, with a total cable length of approximately 2 × 2.5 km and a cable cross-section of 630 mm².
II. On-site Inspection
In October, as the weather gradually turns cooler and the whistles of ships echo from the docks around the Daxie Development Zone, final-stage work on the Huatai project is underway at a brisk pace. Given that the substation construction site is being carried out concurrently with other construction projects at the plant, working conditions on site are relatively challenging.
The cable layer is located on the basement level, with a relatively low ceiling, so personnel descending into it typically have to work in a bent-over, head-down position.
The entire campus is currently under construction, and when we encounter challenges, we have no choice but to find our own solutions. Throughout it all, our leaders have consistently taken the lead and remained on the front lines of the work.
Typically, team members conduct on-site inspections during the day and collaborate with the construction contractor to resolve project-related issues, then return to further refine the design drawings. Everyone wears multiple hats and dedicates themselves wholeheartedly to the project.
III. Evaluation and Outlook
Over nearly a year of production and construction, our design team, while diligently fulfilling our core responsibilities, proactively coordinated with on-site operations. As a large-scale project undertaken by the company, it was characterized by a tight schedule, heavy workloads, and numerous coordinating entities. Under the leadership of company and project management, we tackled challenges head-on and successfully completed all planned tasks on time and to a high standard.
On November 21, 2019, with the active cooperation of all relevant units, the Huatai Substation was officially put into operation.
The newly constructed substation is the first project to be completed within the entire development park; with scaffolding still covering the surrounding buildings, the commissioning of the substation makes it shine even more brightly. When each designer reflects on the painstaking effort that went into every single drawing—those extra shifts and sleepless nights—and then sees the substation now operating safely and reliably, I am confident that all the hardships and sweat of the past will fade away, replaced by a profound sense of pride and accomplishment. Throughout this process, every member of the team has also enhanced their professional skills, truly embodying the saying: “The more you work, the better you become; the busier you are, the more leisure you create.” This marks both an end and a new beginning. We look forward to achieving even greater success in the future!