Breaking News | The 220kV Haihua Substation Expansion and Reconstruction Project for the Fifth Phase of the Daxie Petrochemical Distillate Oil Project (Refining and Chemical Integration Project) Has Been Successfully Put into Operation
Release Date:
2024-03-30
Source:
On March 29, 2024, with the commissioning order issued by the leadership of CNOOC Ningbo Daxie Petrochemical Co., Ltd., the “Daxie Petrochemical Fractional Oil Phase V Project (Refining and Chemical Integration Project)—220 kV Haifa Substation Expansion and Reconstruction Project,” which was invested in at nearly RMB 100 million and undertaken on an EPC basis by Zhejiang Juna Intelligent Power Technology Co., Ltd., officially commenced energization!


The voltage levels of this project are 220 kV/110 kV/35 kV. In this phase, the 220 kV double-busbar configuration will be upgraded and completed; two 220 kV transformers, each with a capacity of 180 MVA, will be expanded; four 110 kV transformers, each with a capacity of 120 MVA, will be expanded; nine 110 kV GIS outgoing lines (double busbar with double section) will be expanded; a 110 kV shunt capacitor reactive power compensation system with a total capacity of 4 × 10 MVar will be expanded; 32 35 kV outgoing lines will be expanded; and six sets of 35 kV grounding transformer assemblies will be expanded.


Our company provided end-to-end, one-stop services for this project, covering preliminary grid connection, engineering design, equipment procurement, construction and commissioning, commissioning and startup, as well as operation and maintenance. In the early stages of the project, with strong support from the power authority, we optimized the grid connection plan and efficiently facilitated the approval and implementation of grid connection opinions and design documentation. Following the official commencement of construction in July 2023, we adhered to the principles of “precision, meticulousness, and dedication,” rigorously enforcing petrochemical safety standards to ensure project safety and strictly complying with State Grid Corporation’s requirements for transmission and transformation projects to guarantee construction quality, thereby advancing the project in a steady and orderly manner. After eight months of dedicated effort, the project successfully passed acceptance by Ningbo Power Supply Company on March 15, 2024, followed by an intermediate handover inspection conducted jointly by the owner, the supervision unit, and the quality inspection station on March 21, 2024. On March 29, 2024, the project was smoothly commissioned and handed over to the owner for operation—delivered with high quality, zero safety incidents, and zero defects.


The successful commissioning of the Phase II expansion of the 220 kV substation for the Daxie Petrochemical Fractional Oil Phase V Refining and Chemical Project has effectively ensured a reliable power supply for the project, and our company’s efforts have been fully recognized and highly commended by the client. On March 29, at the commissioning site on the construction grounds, He Shengru, Chairman of CNOOC Daxie Petrochemical Co., Ltd., personally met with our project team, giving a thumbs-up in approval and repeatedly praising Jueneng Power as “professional and truly outstanding!”


Taking the successful completion of the Phase II EPC general contracting project for the Haihua Substation as a pivotal opportunity, Jueneng Power will remain committed to its corporate mission of “creating maximum value for our customers” and its corporate goal of “delivering high-quality projects and giving back to society.” The company will continuously enhance its comprehensive, full-lifecycle service capabilities across planning and research, survey and design, project management, and operations management, with the aim of becoming China’s leading provider of integrated green power engineering technology services.