Maintenance and Upkeep Project for the 110 kV Substation of Ningbo Huatai Shengfu Polymer Materials Co., Ltd.
Project Scope: 2 main transformers, 7 110 kV GIS switchgear cabinets, 23 35 kV GIS switchgear cabinets, 2 sets of SVG dynamic reactive power compensation devices, and other electrical equipment; Project Location: Beilun District, Ningbo Scope of Work: Maintenance and Upkeep
Category:
Power Plant System Operation and Maintenance
Keywords:
Maintenance and Upkeep Project for the 110 kV Substation of Ningbo Huatai Shengfu Polymer Materials Co., Ltd.
Service Hotline
Product Details
Project scope: two main transformers, seven 110 kV GIS switchgear cabinets, twenty-three 35 kV GIS switchgear cabinets, two sets of SVG dynamic reactive power compensation units, and other electrical equipment.
Project Location: Beilun, Ningbo
Project Scope: Maintenance and Upkeep
Related Products
Beilun Zhejiang Electric Power Photovoltaic-Storage Fully Distributed Project
Scale: 88 kW photovoltaic system + 100 kW/215 kWh energy storage system + charging stations (60 kW + 120 kW) Project Scope: EPC general contracting Location: Beilun District, Ningbo City Completion Date: December 2023
View DetailsProject Scope: Four distribution substations with a total installed capacity of 16,000 kVA and 96 charging piles, each rated at 120 kW. Project Location: Jiangbei District, Zhenhai District, and Yinzhou District of Ningbo City. Scope of Work: EPC. Commissioning Date: 2022.
View DetailsProject Scope: Two distribution rooms with a total installed capacity of 2,500 kVA and 30 charging piles, each rated at 80 kW. Project Location: Beilun District and Yinzhou District, Ningbo City. Scope of Work: EPC. Commissioning Date: 2021.
View Details2017 BYD Pure Electric Bus Charging Infrastructure Construction Project
Project Scope: Two distribution substations with a total installed capacity of 17,600 kVA and 130 charging piles, each rated at 120 kW. Project Location: Jiangbei District, Zhenhai District, and Yinzhou District of Ningbo City. Project Scope: EPC. Commissioning Date: 2017.
View DetailsProject Scope: The transmission line starts at the Daxie 220 kV Leng’ao Substation in Beilun and ends at the Wanhua 110 kV Logistics Substation. The double-circuit cable line has a total length of 1.78 km, while the optical cable is a 24-core non-metallic flame-retardant fiber optic cable with a total installed length of 2.3 km, connecting the Leng’ao Substation to the Logistics Substation. Project Location: Beilun District, Ningbo Project Scope: Maintenance and Upkeep
View DetailsProject Scope: 2 main transformers, 7 110 kV GIS switchgear cabinets, 23 35 kV GIS switchgear cabinets, 2 sets of SVG dynamic reactive power compensation devices, and other electrical equipment; Project Location: Beilun District, Ningbo Scope of Work: Maintenance and Upkeep
View DetailsProject Scope: Four 180 MVA 220 kV transformers, six 120 MVA 110 kV transformers, and other ancillary equipment and external power lines. Project Location: Beilun District, Ningbo Project Scope: Maintenance and Upkeep
View DetailsNingbo Haoyang New Materials Technology Co., Ltd. Distributed Photovoltaic Power Generation Project
Capacity: 7,200 kW Project Scope: EPC General Contracting + Power Plant O&M Location: Yuyao City, Ningbo Municipality Completion Date: December 2022
View DetailsShenzhou Textile Photovoltaic Curtain Wall Demonstration Project
Project Scale: 500 square meters Project Location: Ningbo, Zhejiang Province Scope of Work: EPC General Contracting Commissioning Date: 2021
View Details220 MW Photovoltaic Power Generation Project in Shiqiao Town, Taibai Lake New Area
EPC General Contracting Project for Survey and Design Services Installed Capacity: 220 MW Project Location: Jining, Shandong Province Scope of Work: Design Commissioning Date: 2025
View DetailsHuaxi New Energy Technology Co., Ltd. 120 MW Photovoltaic Power Generation Project
Installed capacity: 120 MWp, grid-connected at 110 kV Project location: Yanzhou, Shandong Province Scope of work: EPC Commissioning date: 2019
View Details8,441.95 kWp + 3 MW/6 MWh Solar-plus-Storage EPC Project Project Scale: 8,441.95 kWp of photovoltaic capacity plus a 3 MW/6 MWh energy storage system Project Location: Rugao County, Nantong City, Jiangsu Province Scope of Work: EPC General Contracting Commissioning Date: 2023
View DetailsEPC Project for the 11.6 MW/22.35 MWh Energy Storage Project at Xiangshan Huaxiang
Project Scale: 11.6 MW/22.35 MWh energy storage project Project Location: Xiangshan District, Ningbo City, Zhejiang Province Scope of Work: EPC general contracting Commissioning Date: Under construction; expected in 2025
View DetailsNingbo Xusheng Automobile Co., Ltd. (Third Factory) Photovoltaic-Storage Power Generation Project
The photovoltaic–energy-storage power station project of Ningbo Xusheng Automobile Co., Ltd. (Third Factory) has an energy-storage capacity of 0.5 MW/1 MWh and is located in the Beilun District of Ningbo City. Our company is responsible for providing EPC turnkey services for this project, which was successfully completed and put into operation in November 2020. This project marks Zhejiang Province’s first user-side megawatt-scale integrated photovoltaic–energy-storage station.
View Details1.2 MW/2.4 MWh Smart Energy Storage Project on the User Side of Sanwei Datong
This project is a 1.2 MW/2.4 MWh smart energy storage system on the user side in Datong, with a storage capacity of 1.2 MW/2.4 MWh. The project is located in Haiyan County, Jiaxing City, and our company is responsible for providing EPC general contracting services. The project was successfully completed and put into operation in 2023.
View DetailsJiaxing Samsung Textile Co., Ltd. 0.5 MW/1 MWh Smart Energy Storage Project
This project is the 0.5 MW/1 MWh smart energy storage system for Jiaxing Samsung Textile Co., Ltd., with a battery storage capacity of 0.5 MW/1 MWh. Located in the Xuzhou District of Jiaxing City, our company is responsible for providing EPC turnkey services for this project. The project was successfully completed and put into operation in 2023, marking the first user-side smart energy storage project in the Xuzhou District of Jiaxing City.
View DetailsNingbo Peiyuan Co., Ltd. 1 MW/2 MWh User-Side Energy Storage Project
Ningbo Peiyuan Co., Ltd.’s 1 MW/2 MWh user-side energy storage project has a storage capacity of 1 MW/2 MWh and is located in Dongqiao Town, Haishu District, Ningbo City. Our company is responsible for providing EPC turnkey services for this project, which was successfully completed and put into operation in 2022.
View DetailsProject Scale: 200 MW/400 MWh Energy Storage Project Location: Wuyi, Jinhua Project Scope: Design Commissioning Date: Completed
View DetailsNinghai Shuangyili Power Supply Project
This project is located in Ninghai County, Ningbo City, and is currently under construction. It involves the construction of a new 3.1-km-long 35-kV double-circuit overhead transmission line and a new 4.8-km-long single-circuit cable line. The overhead conductors will be JL/LB20A-240/30 aluminum-clad steel-core aluminum stranded conductors, the overhead ground wires will consist of two 24-core fiber-optic composite overhead ground wires, and the cables will be YJV-26/35-1×300 mm² cross-linked polyethylene-insulated power cables.
View DetailsThis project is located in Laizhou City, Shandong Province, and involves substantial construction work. The new 35 kV four-circuit overhead line has a total length of 7.6 km, while the double-circuit overhead line spans 0.5 km. The conductors are JL/LB20A-240/30 aluminum-clad steel-core aluminum stranded conductors, and the overhead ground wire consists of two 48-core fiber-optic composite overhead ground wires.
View DetailsMajor Overhaul of Aging Tower 7723 on State Grid Zhejiang Ningbo 110kV Caiyin Line 1297
This project is located in Yinzhou District, Ningbo City, and has now been completed and put into operation. The newly constructed line route has a length of 0.301 km. The new transmission conductors are JL/G1A-300/40 steel-core aluminum stranded conductors, and the two ground wires are both OPGW-13-90-1 optical fiber composite overhead ground wires.
View DetailsThis project is located in the Jiangbei District of Ningbo City and has now been completed and put into operation. The newly constructed transmission line has a length of 0.751 km. The new conductor is JL/G1A-300/40 steel-core aluminum stranded wire, and both ground wires are OPGW-13-90-1 optical fiber composite overhead ground wires.
View DetailsMajor Overhaul of Aging Tower 7722 on State Grid Zhejiang Ningbo 110kV Tunheng Line 1355
This project is located in Cixi City, Ningbo Municipality, and has now been completed. The scope of work includes the replacement of conductors and hardware at two locations on the 110 kV Tunheng Line 1355 that currently use explosion-pressed tubes: specifically, the three-phase conductors between Tower 8 and Tower 9, and the B and C phase conductors between Tower 22 and Tower 27. The total length of the replaced conductor section is 1.505 km, with the new conductors being JL/G1A-240/40 steel-core aluminum stranded conductors. The ground wires are all OPGW-10-50-1 optical fiber composite overhead ground wires, with a total length of 8.23 km.
View DetailsNingbo 110kV Juzi–Beilun Power Line 6–Power Line 7 Relocation and Reconstruction Project
This project is located in Beilun District, Ningbo City, and has now been completed. A new double-circuit overhead transmission line with a total length of 0.235 km has been constructed, utilizing JL/G1A-300/40 steel-core aluminum stranded conductors for the phase conductors and two OPGW-13-90-1 optical ground wires for the shield wires.
View DetailsThis project is located in Taizhou City and has now been completed. The scope of the project involves the installation of 360 sets of line surge arresters on seven transmission lines, including the 220 kV Jingzhou–Zhoushan Line 24F4.
View DetailsThis project is located in Beilun District, Ningbo City, and is currently under construction. It involves the construction of 2.6 km of new double-circuit overhead lines and 2.74 km of new single-circuit overhead lines. Conductor: 2×JL/LB20A-630/45 aluminum-clad steel-core aluminum stranded conductor is used. Ground wire: Two OPGW-120 optical fiber composite ground wires are employed.
View DetailsState Grid Zhejiang Taizhou 220kV Guanghai Line 2352 Guyed Tower and Ground Wire Renovation Project
This project is located in Linhai City, Taizhou. The project has now been completed. The renovation involves the construction of two new single-circuit angle-steel towers and the replacement of two ground wires between spans 24 and 43 with JLB20A-70 aluminum-clad steel stranded conductors, spanning a total route length of 8.355 kilometers. In addition, two existing single-circuit guyed towers have been dismantled.
View DetailsReconstruction Project for 220kV Jiaoda Line 2311 and Jiaopeng Line 2314, Sections 42–44
This project is located in Zhenhai District, Ningbo City, and is currently under construction. The project is being built to the “three-span” standard, with a newly constructed double-circuit overhead transmission line measuring 0.612 km in length. Conductor: 2×JL/G1A-630/45 steel-core aluminum stranded conductor. Ground wire: two 72-core OPGW optical fiber composite overhead ground wires are used.
View DetailsThis project is located within Ninghai County and Fenghua District of Ningbo City and has now been completed. The 220 kV Xikou Traction Substation is supplied with power from the 220 kV Yancang Substation, and the newly constructed transmission line has a total length of 42.75 km. Conductor: 2×JL3/G1A-400/35. Ground wire: two 36-core OPGW cables.
View DetailsThe Jianfa Yangyun project is located in the Jiangbei Wantou area, at the intersection of Xiajiang Road and Wantou Road, covering a land area of 18,160 square meters with a total floor area of approximately 70,000 square meters.
View DetailsThe Meixu Historic District Protection and Development Project along the Yongjiang River Bank in Ningbo High-tech Zone covers a total land area of 23.4 hectares, bounded to the north by the southern bank of the Yongjiang River, to the south by the planned Yongjiang Avenue, to the west by a point 245 meters west of the western bank of Dujiabridge, and to the east by a point 72 meters east of the eastern bank of the shipyard. The project has a total electrical load capacity of approximately 3,000 kVA. Our company was responsible for the external power connection works and the construction of a dedicated distribution substation for this project, both of which have now been completed and put into operation.
View DetailsFulda (Ningbo) Intelligent Optoelectronics Co., Ltd. has invested RMB 1.05 billion in a new project in the Ningbo Qianwan New Area, which is expected to generate an additional output value of approximately RMB 2.072 billion upon commissioning. The project’s total electricity demand is about 18,000 kVA, with the first phase requiring a connected capacity of 7,200 kVA. The external power connection works for this project, undertaken by our company, also represent the first instance in which the New Area Management Committee and the user have jointly completed construction and commissioned the facility under the “Power Cost-Sharing Mechanism.”
View DetailsEPC Project for the 220 kV Substation of Daxie Petrochemical Engineering Co., Ltd.
This project is an expansion project: 220 kV Section: (1) Increase the capacity of the 220 kV main transformers by 2 × 180 MVA, bringing the total capacity after the expansion to the final design level of 4 × 180 MVA. (2) Reactive power compensation: This phase of the expansion adds 4 × 10 Mvar of capacitive reactive power and 2 × 10 Mvar of inductive reactive power. Following this phase of the expansion, the reactive power compensation will reach the final design level of 8 × 10 Mvar of capacitive reactive power and 4 × 10 Mvar of inductive reactive power.
View DetailsChengde Yudaokou Ranch 100 MW Photovoltaic Project (15 MW/30 MWh)
The 100 MW photovoltaic project at the Yudaokou Ranch in Chengde involves a 100 MW AC-side installed capacity and a 15 MW/30 MWh energy storage system. Located in Chengde City, Hebei Province, our company is responsible for the design services for this project, which was successfully completed and commissioned at the end of 2023.
View DetailsNingbo Bank Jiangbei Data Center 35kV Yongxing Substation Project
This project is located in the Gateway Economic Development Zone of Jiangbei District, Ningbo City, and was successfully completed and put into operation in November 2018. The 35 kV Yongxing Substation is an all-indoor substation with a main transformer capacity of 2 × 16 MVA, expanding to a final capacity of 2 × 16 MVA + 2 × 10 MVA. The 35 kV system adopts a single-busbar sectionalized configuration, with two incoming feeders and four outgoing feeders, using cable-based connection for both incoming and outgoing lines. The 10 kV system also employs a single-busbar sectionalized configuration, with two incoming feeders connected directly to the busbar and eight outgoing feeders, all utilizing cable connections.
View DetailsScope of the renovation: installation of one new 110 kV main transformer and associated equipment, one new 110 kV SF6 switchgear bay, installation of 110 kV cables and accessories within the substation, and corresponding upgrades to the secondary control system.
View DetailsScope of the renovation: installation of one set of 110 kV main transformer and associated equipment, one new 110 kV SF6 switchgear bay, installation of 110 kV cables and accessories within the substation, and corresponding upgrades to the secondary control system.
View DetailsRenovation scope for the 110 kV Haoyang Substation: Replace Main Transformer No. 1, with a voltage rating of 110/10 kV, with a 110 kV/35 kV unit rated at 50 MVA; replace the 10 kV switchgear with 35 kV switchgear; carry out on-site upgrade and retrofit of the SVC dynamic reactive power compensation system; and implement corresponding upgrades to the secondary control system.
View DetailsNew Construction Project for the Zhishan 110kV Substation
This project is the Zhishan 110 kV Transmission and Transformation Project in Ningbo City, with a main transformer capacity of 2 × 50 MVA and a semi-indoor design. The project site is located in Yangming Subdistrict, Yuyao City. Our company’s design institute is responsible for the electrical secondary construction drawing design and as-built drawing preparation technical services for this project. The project was successfully completed and put into operation in 2020.
View Details220kV Tongshan Substation Renovation Project
This project involves the installation of two new 10 MVA shunt reactors at the reserved site within the Tongshan Substation’s 35 kV yard, the renovation of two 35 kV switchgear bays, and the addition of corresponding protection, measurement, and control devices to the electrical secondary system. The renovation was completed in December 2019.
View Details220kV Cuiping Substation 220kV Busbar Sectionalization Renovation Project
This project involves the installation of one new 220-kV main bus section bay, one new 220-kV bus-tie second bay, and one new 220-kV main bus section II bus voltage transformer bay at the reserved site within the Cuiping Substation’s 220-kV yard. In addition, the secondary electrical portion of the project includes the addition of one 220-kV bus-section protection panel, one 220-kV bus-section measurement and control panel, one 220-kV bus-tie protection panel, one 220-kV bus-tie measurement and control panel, one 220-kV bus-setting measurement and control panel, and one set of 220-kV bus differential protection equipment. The renovation was completed in June 2021.
View DetailsThis project is the Zeshan 110 kV Transmission and Transformation Project in Ningbo City, with a main transformer capacity of 2 × 50 MVA and a semi-indoor configuration. The project site is located in Guanhaiwei Town, Cixi City, and our company’s design institute is responsible for the civil engineering construction drawing design and as-built drawing preparation technical services. The project was successfully completed and put into operation in 2018.
View Details110kV Main Substation Project of Ningbo Huatai Shengfu Polymer Materials Co., Ltd.
This project is the 110 kV main substation for Ningbo Huatai Shengfu Polymer Materials Co., Ltd., with a main transformer capacity of 2 × 63 MVA. The project is located in the Daxie Development Zone of Ningbo, and our design institute is responsible for the preliminary site survey, construction drawing design, as-built drawing preparation, and engineering management consulting services. The project was successfully completed and put into operation in 2019.
View DetailsThis project was completed and put into operation on December 29, 2018. The 110 kV Huaxi Substation is a semi-indoor substation with two main transformers, each rated at 63 MVA. The main transformers are three-phase oil-immersed, double-winding, on-load tap-changing, self-cooled step-up power transformers, operating at a voltage level of 35/110 kV and configured as SZ11-63000/110. The 110 kV switchgear utilizes indoor GIS equipment, and the 110 kV system employs a single-busbar configuration. On the 110 kV side, there are two incoming feeder circuits for the main transformers and one outgoing circuit. The 35 kV system also uses a single-busbar configuration, with 12 incoming feeder circuits from the photovoltaic plant; reactive power compensation is provided by dynamic reactive power compensation SVG units, with a total capacity of 4 × (±7.5 MVAR).
View DetailsNingbo Iron & Steel Co., Ltd. 220kV Yonggang Substation Capacity Expansion and Renovation Project
This project involves the expansion of Main Transformer No. 4, with a rating of 50 MVA. The transformer is a three-phase, step-down, on-load tap-changing, double-winding unit, operating at voltage levels of 220 kV/35 kV and designated as SFS-50000/220 kV. In the long term, the 220 kV outgoing lines are planned to comprise six circuits, configured in a double-bus, double-section arrangement; currently, three circuits have been commissioned, utilizing a double-bus configuration with indoor GIS equipment. During this phase, the substation control-layer equipment and the dispatch data network equipment will be upgraded concurrently. Our company is responsible for the preliminary site survey, construction drawing design, and as-built drawing design technical services for this project. The project was successfully completed and put into operation in December 2018.
View DetailsNingbo Haoyang New Materials Technology Co., Ltd. 110kV Substation
This project is the 110 kV user substation for Ningbo Haoyang New Materials Technology Co., Ltd., with a main transformer capacity of 1 × 50 MVA + 1 × 80 MVA. The project is located in the Binhai New City of the Yuyao Economic Development Zone. Our design institute is responsible for the preliminary design, construction drawing design, and preparation of as-built drawings for this project. The project was successfully completed and put into operation in 2017.
View DetailsAnji Caodang Reservoir 50 MWp Fish-Solar Complementary Photovoltaic Power Generation Project
This project, the 50 MWp Fish–Solar Complementary Photovoltaic Power Generation Project at the Caodang Reservoir in Anji, undertaken by State Power Investment Corporation Sunny Anji New Energy Co., Ltd., is scheduled for completion and commissioning in 2017. The project is located in Anji County, Huzhou City, Zhejiang Province, and is owned by State Power Investment Corporation Sunny Anji New Energy Co., Ltd.
View DetailsXiangshan China Energy Conservation Tailai Environmental Protection Energy Co., Ltd. was established on December 12, 2014, with its registered address at No. 29 Dongtangshan Road, Dandong Subdistrict, Xiangshan County, Ningbo City. The company was founded through investment by three shareholders: China Environmental Protection Group Corporation, Zhejiang Tailai Environmental Protection Technology Co., Ltd., and Taiyuan Chenfeng Environmental Protection Engineering Co., Ltd., with a registered capital of RMB 100 million. The company plans to construct a municipal solid waste incineration power plant on the Shuitong’ao Environmental Industrial Plot in Dongchen Township, Xiangshan County (Plot No. 017-925-0434). The project will be implemented in two phases: Phase I entails the construction of a 600-ton-per-day waste incineration production line along with associated flue-gas purification systems, while also reserving space for an additional 300-ton-per-day waste incineration production line.
View DetailsThe Ningbo Municipal Government’s rooftop photovoltaic demonstration project is located at the Ningbo Administrative Service Center in Zhejiang Province and was funded and constructed by the Ningbo Municipal Government as a pilot initiative. The project seamlessly integrates photovoltaic technology with the garden roof of the administrative service center, creating an eco-friendly and sustainable facility. This project has played a pivotal role in advancing the development of public-sector PV installations in Ningbo.
View DetailsNingbo University Photovoltaic Power Generation Project
The 400 kW rooftop distributed photovoltaic project at the Ningbo University Library is located on the university campus and was funded and constructed by Ningbo University. Construction commenced in May 2016 and was completed in December 2016. The project adhered to stringent construction quality standards and, as part of the overall library renovation, was nominated for the “Yongjiang Cup” award.
View DetailsHuaqin Rubber Industry Group’s 120 MW Rooftop Photovoltaic Power Generation Project
The 120 MW rooftop photovoltaic power project of Huaqin Rubber Industry Group is located within the premises of the Huaqin Group in Yanzhou District, Jining City, Shandong Province. It was developed and invested in by Zhejiang Hongxi Energy Co., Ltd. The project involves the construction of a distributed PV power plant on 1.2 million square meters of rooftops across the Huaqin Industrial Park, along with a 110 kV substation. To date, this project represents the largest distributed rooftop PV installation in China. Construction commenced in March 2018, and the entire capacity was connected to the grid in December 2018.
View Details9 MWp Distributed Photovoltaic Power Generation Project in Yuyao Industrial Park
The 9 MW project in the Yuyao Industrial Park is located in Langxia Subdistrict, Yuyao City. Funded and constructed by Ningbo Energy Group, the project commenced in May 2015 and was completed in December. The entire project encompasses the Duohong, Gengda, Bailong, Huaxin, Yixincheng, and Jiefeng plant areas. Our company undertook the project from feasibility study and design through preliminary design to full engineering general contracting, successfully delivering the works on time, to the required quality, and in accordance with specifications.
View DetailsCixi Longshan Tidal Flat 18 MWp Ground-Mounted Solar Power Project
The 18 MW ground-mounted solar power project at the Longshan Tidal Flat in Cixi is located on idle land within the Longshan Industrial Park in Cixi City and was developed and invested in by Zhejiang Hongxi Energy Co., Ltd. The project utilizes 300 mu of underutilized land to construct a photovoltaic ground-mounted power station, thereby implementing a new production model that combines power generation above with agricultural cultivation below. From initial consultation and design through to final construction, the client entrusted our company with the entire scope of work, and the project achieved full-capacity grid connection in December 2017.
View DetailsCixi 5.3 MWp Distributed Photovoltaic Power Generation Project
The 5.3 MW distributed photovoltaic project in Cixi is located in the Cixi High-Tech Industrial Park. Funded and constructed by Ningbo Energy Group, the project commenced in March 2016 and was completed in June. The entire project is divided into six sub-areas: the Zhonghuan Plant Area, the Cixing Plant Area, the Astronergy Plant Area, the Zhongda Plant Area, the Jisheng City Plant Area, and the Henghe Plant Area. Our company undertook the project from feasibility study and design through preliminary design to general engineering contracting, successfully delivering the work on time, to specification, and with assured quality.
View Details40 MWp Mountain Ground-Mounted Solar Power Plant Project in Zhanjia Town, Longyou County
Located in Zhanjia Town, Longyou County, Zhejiang Province, this project is invested in and constructed by China Machinery Guoneng Power Investment Co., Ltd., with a total installed capacity of 40 MWp and was connected to the grid on June 30, 2016.
View DetailsThe Ningbo Municipal People’s Procuratorate Photovoltaic Demonstration Project is located in the Eastern New City of Ningbo, with an installed capacity of 60 kW. The project is invested in by the Ningbo Municipal People’s Procuratorate and designed and undertaken on a turnkey basis by Zhejiang Juna Intelligent Power. The project was connected to the grid and put into operation in 2017, generating 60,000 kWh of green electricity annually.
View DetailsNingbo Jinji Strong Magnet Co., Ltd. 1998 36 kWp Rooftop Photovoltaic Power Generation Project
Recently, Zhejiang Jueneng Smart Power successfully entered into a partnership with Ningbo Jinji Strong Magnet Co., Ltd., marking another significant step forward in the continuous upgrading of its photovoltaic contracting business. Ningbo Jinji Strong Magnet is a company dedicated to the research and development of sintered neodymium-iron-boron magnets and serves as an implementing entity for China’s National 863 Program (National High-Tech Research and Development Program). In response to the national call for energy conservation and emissions reduction, Ningbo Jinji Strong Magnet has chosen Jueneng Power to undertake photovoltaic installation, thereby replacing traditional high-pollution, high-emission energy sources. Through in-depth collaboration with our company, the partnership not only promotes green and energy-efficient practices but also continuously unleashes robust vitality, working together to build a solid environmental protection barrier.
View DetailsFormosa Plastics Group Thermoelectric (Ningbo) Co., Ltd. Photovoltaic Equipment Investment Project
The Photovoltaic Equipment Investment Project of Formosa Plastics Group Thermal Power (Ningbo) Co., Ltd. is a photovoltaic project invested in by Formosa Plastics Group (Ningbo) Co., Ltd. It marks the first collaborative project between our company and Formosa Plastics Group, as well as the group’s inaugural PV project on the Chinese mainland. Located on the roof of the coal yard building at the Formosa Thermal Power Plant within the Formosa Industrial Zone in Xiapu Subdistrict, Beilun District, Ningbo City, Zhejiang Province, the project has a total installed capacity of 2,053.8 kWp. It was designed and constructed by our New Energy Team, with the project design and construction quality—under the leadership of the New Energy Department—receiving full approval from the client. The system was successfully connected to the grid and began generating power on November 2, 2022.
View DetailsThis project is located in Grid NBHWZN-01 of the Southern Zone of the Smart Industrial Park, which is bounded by Shitang Hengjiang Road, Xingci Eighth Road, Binhai First Road, and Xingci Sixth Road. The area is predominantly industrial land, with a Class B power supply zone. The grid is supplied by the 110 kV Haixing Substation, Yueci Bin Substation, and Binhai Substation, covering an area of 13.65 square kilometers. The current load stands at 52.78 MW. At present, the network configuration in this area—comprising the 10 kV Hangzhi B509 Line, Yuebin B523 Line, Yongheng B251 Line, and Jiutang B248 Line—is non-standard. In 2016, the maximum load factor on the Hangzhi B509 Line reached 92.86%, resulting in poor power supply reliability. Upon completion of this project, a new 007 line will be tapped from the No. 3 main transformer at the 110 kV Yueci Substation, and the Hangdi B516 Line, together with the 10 kV XinHai X104 Line and Chuangyuan X114 Line from the 110 kV Xinzhou Substation, will form one standard double-ring network. Simultaneously, the branch loads currently served by the heavily loaded Hangzhi B509 Line will be transferred to this new network, while the existing Hangzhi B509 Line, Yuebin B523 Line, Yongheng B251 Line, and Jiutang B248 Line will also be reconfigured into another standard double-ring network. In this way, two standard double-ring networks will be established, thereby achieving the target network configuration. As a flagship project representing the Ningbo Power Supply Company of State Grid Corporation of China, this project was submitted for the Zhejiang Provincial Electric Power Company’s evaluation of outstanding consulting achievements in power grid planning, feasibility studies, and specialized research, and was awarded the First Prize in the 2017 Distribution Network Feasibility Study category by the Zhejiang Provincial Electric Power Company.
View Details10 kV Weitu B691 Line Renovation Project in Ningbo Hangzhou Bay New Area
The 10-kV Weitu B691 line, fed by the 110-kV Bailu Substation, primarily supplies power to the eastern reclamation area of the New District, covering a reclaimed land area of 67 square kilometers. Currently, the line is overhead, with the main feeder using LGJ-150 conductors and most branch circuits employing LGJ-120 or smaller conductors, resulting in relatively small cross-sectional areas. In 2015, the maximum load factor reached 63%. It is anticipated that the installed capacity for new infrastructure projects in the reclamation area between Piers 11 and 12 will reach 9,000 kVA, a demand that the existing line can no longer accommodate. To meet the growing regional load and enhance line interconnection, the renovation project for the 10-kV Weitu B691 line in the Ningbo Hangzhou Bay New Area takes into account the current overhead configuration of the 110-kV Bailu Substation–10-kV Weitu B691 line, its operational status, load registration data, and route alignment. The project involves undergrounding the main section of the Weitu B691 line from Pole No. 1 to Pole No. 20-20, constructing six new ring-main units along the route, and laying 3.4 kilometers of cable, thereby improving both the region’s power supply capacity and reliability. In addition, this project was selected as a representative initiative of the Ningbo Power Supply Company of State Grid Corporation of China for the Zhejiang Provincial Electric Power Company’s Quality Project Evaluation, ultimately ranking among the top 20 high-quality distribution network construction and renovation projects of State Grid Zhejiang Electric Power Co., Ltd. for 2017.
View DetailsThis project is located in the Zhenhai Petrochemical Zone, bounded by Wanghai South Road to the east, Haitian Middle Road to the west, Lanshan Road to the south, and Tongtu Road to the north. The project comprises two 220-kV Dian’gen Substation and two 220-kV Yanhai Substation, each of which supplies two 35-kV circuits to the Xiepu 35-kV Switchyard. <br/> (1) Route from the 220 kV Dian’gen Substation to the Xiepu 35 kV Switchyard: A double-circuit cable from the 220 kV Dian’gen Substation runs to Cable Terminal Tower No. 1; after the cable is brought up, an overhead line extends to the tower on the east side of Zhenpu Road, turns left and runs parallel to Lanshan Reservoir toward the north, then connects to Cable Terminal Tower No. 17, where the cable is brought down. The route continues along the north-side roadbed of Wanghai South Road to Xingye Road and Fengxiang Road, ultimately reaching the Xiepu 35 kV Switchyard. <br/> (2) Route from the 220 kV Coastal Substation to the Xiepu 35 kV Switchyard: The double-circuit cable outgoing from the 220 kV Coastal Substation turns left at the intersection of Yuejintang Road and Haifeng Road, then turns right at the intersection of Haitian Middle Road and Haifeng Road, and finally runs along the west-side roadbed of Haitian Middle Road to the Xiepu 35 kV Switchyard.
View DetailsNingbo Xuhui Real Estate – South and North Sections of the Wanzhong Plot Project
The Wanzhong Plot is located in Jishigang Subdistrict, Haishu District, Ningbo City. Developed jointly by the Haishu District People’s Government and Sunac China, the project is a key initiative for Haishu District. With a total construction area of 440,000 square meters, it comprises residential units and a kindergarten. Our company has been contracted to undertake all electrical installation works for the entire plot, with completion scheduled for 2022.
View Details220kV Xianxiang Substation–Ningbo Boway 35kV Power Pipeline Project
Ningbo Boway New Materials Co., Ltd. is a wholly owned subsidiary of Ningbo Boway Alloy Materials Co., Ltd. and was established in 2018. The company’s products are primarily used in high-end markets such as the smart internet, smart terminal devices, new-energy vehicles, and semiconductors, meeting the needs of Fortune Global 500 companies and industry-leading benchmark enterprises. <br/> This project is the 35 kV Boxin Substation transmission and transformation works constructed to support Ningbo Bowei New Materials Co., Ltd.’s annual production project for 50,000 tonnes of special alloy strip. The main transformer capacity is 2 × 16,000 kVA, with a single-circuit power supply. A new 35 kV transmission line is built to connect to the 35 kV bay at the 220 kV Xianxiang Substation. The new line employs a combined cable-and-overhead installation method, with a total length of approximately 10.96 kilometers. The entire substation adopts an all-indoor design, with protection and monitoring equipment arranged in a hierarchical, distributed configuration and a comprehensive automated control scheme.
View Details35kV Substation Project of Ningbo Rongbai New Energy Technology Co., Ltd.
Ningbo Rongbai New Energy Technology Co., Ltd. is a high-tech new-energy-materials enterprise controlled by Beijing Rongbai Investment Holding Co., Ltd., and operates as a multinational group specializing in the R&D and commercialization of cathode materials for lithium-ion batteries. To support the company’s development, it has undertaken the “Annual Expansion and Upgrade Project for a 33,000-ton-per-year Production Line of Ternary Cathode Materials for Power Lithium-Ion Batteries,” which includes the construction of a 35-kV substation with two main transformers, each rated at 10 MVA, one 35-kV incoming feeder, and seven 10-kV outgoing feeders. The substation is a three-story above-ground structure, with a total project investment of approximately RMB 22 million. Our company provides end-to-end technical services for this project, including the feasibility study report on the grid connection system, preliminary design, and detailed civil and electrical construction drawings.
View DetailsNingbo Oriental Cable Co., Ltd. 35kV Dedicated Transformer Connection System
Ningbo Oriental Cable Co., Ltd. has constructed a new 35-kV substation to support the implementation of the “Demonstration Project for the Application of High-End Marine Energy Equipment Systems.” The grid connection scheme for this project is as follows: a new 35-kV transmission line will be built to connect to the 220-kV Houdun Substation; two main transformers, each with a capacity of 12.5 MVA, will be installed; one 35-kV incoming feeder and eleven 10-kV outgoing feeders will be provided. The substation adopts an all-indoor layout and is configured as a single-story above-ground structure. During the design phase, multiple optimization iterations were conducted in consultation with the client to achieve a compact and rational electrical layout, thereby minimizing the footprint and reducing capital investment.
View DetailsOverall Distribution Network Planning for the 13th Five-Year Plan Period in Kaili, Guizhou Province
From October 2014 to February 2015, the “13th Five-Year” distribution network planning for Kaili City in Qiandongnan Miao and Dong Autonomous Prefecture, Guizhou Province, involved comprehensive grid planning for Kaili City and its 15 subordinate counties and county-level districts; our company undertook the planning work for six of these counties and districts.
View Details