Blogs Details
Getting to Know Power Design Engineers
Release Date:
2019-11-06
Source:
Tall buildings rising from flat ground are constructed brick by brick; bountiful harvests depend on diligent cultivation. Without accumulating small steps, one cannot reach a thousand miles—every success begins with humble beginnings. As the saying goes, “A sharp sword is forged through relentless sharpening,” and diligent study and research serve as the catalyst for progress. Steadfastness, meticulousness, and a willingness to delve deeply into one’s work are essential qualities of a qualified employee. Moreover, striving for excellence yields mid-level results, while aiming only for mediocrity leads to subpar outcomes—this is the guiding principle upheld by every electrical engineering designer at the Design Institute of Zhejiang Jueneng Power Engineering Co., Ltd.
I. On-site Survey
The 120 MWp distributed photovoltaic power generation project of Huaqin Rubber Industry Group is located within the Huaqin Industrial Park in Yanzhou District, Jining City, Shandong Province. The project utilizes the rooftops of 44 existing factory buildings and newly constructed buildings to construct a photovoltaic power plant. The proposed facility is a high-efficiency solar photovoltaic power plant with an installed capacity of approximately 120 MWp, which will be fully integrated into the grid at 110 kV and connected to the State Grid near the industrial park.
In May, Shandong was dry and sweltering, so the delegation arrived early in the morning at Huaqin Rubber Industry Group for a site inspection.
When most property owners invest in rooftop photovoltaic power plants, they place great emphasis on project feasibility, installed capacity, investment returns, and cooperation models. However, distributed rooftop site surveys are part of the preliminary work, and professional survey records are a critical factor in evaluating the power plant. Through on-site inspections, relevant roof data are collected to lay the groundwork for optimizing the design scheme and conducting precise analyses of investment returns.
Upon investigation, and taking into account factors such as solar irradiance, site conditions, and the power-generation efficiency of photovoltaic modules, the Huakin Rubber Industry Group’s 120 MWp rooftop photovoltaic power plant project is planned with a total installed capacity of 119.9965 MWp: Phase I has an installed capacity of 60.0535 MWp, covering approximately 520,940 m² of roof area; Phase II has an installed capacity of 59.943 MWp, covering approximately 502,860 m² of roof area. Calculations indicate that the annual average grid-connected electricity output of this photovoltaic project will be 130.2271 million kWh, with a total generation over 25 years of approximately 3,255.6786 million kWh.
II. Electrical Design
The electrical design process is complex and painstaking, with an endless stream of issues to be resolved. Yet every “Junoer” adheres to the principle that striving for the highest standards yields mid-level results, while aiming for mediocrity only leads to subpar outcomes—thereby setting exceptionally high standards for themselves and relentlessly pursuing perfection in their drawings, forging ahead with unwavering dedication in their work.
In the electrical primary design for this project, mainstream 325 W polycrystalline silicon PV modules are selected. Specifically, Phase I will deploy 184,780 units of 325 W polycrystalline silicon modules, while Phase II will deploy 184,440 units. Following a technical and economic comparison of on-site step-up substation configurations, Phase I of this project will be equipped with 19 units of 1,600 kVA packaged step-up transformers, 18 units of 1,250 kVA packaged step-up transformers, 5 units of 1,000 kVA packaged step-up transformers, and 1 unit of 500 kVA packaged step-up transformer; Phase II will be equipped with 25 units of 1,600 kVA packaged step-up transformers, 13 units of 1,250 kVA packaged step-up transformers, 2 units of 1,000 kVA packaged step-up transformers, and 2 units of 500 kVA packaged step-up transformers.
This photovoltaic power plant is planned and designed to include one 110 kV step-up substation with a transformer capacity of 2 × 60 MVA. The substation will be connected to the 110 kV bay of the 220 kV Maqing Substation via a single 110 kV transmission line, which is approximately 2.5 km in length.
This photovoltaic power plant is designed in accordance with the “unmanned” (minimally staffed) principle. The plant employs a computer-based monitoring system as its primary monitoring approach. A comprehensive automation system is installed throughout the entire photovoltaic power plant, providing functions such as protection, control, communication, and measurement. This system enables fully integrated, multi-functional automated management of the photovoltaic generation system and the switchyard, as well as remote measurement and remote signaling between the photovoltaic power plant and the regional dispatch center, and supports monitoring and management by the power generation company.
III. Evaluation and Outlook
Thanks to the concerted efforts of all involved over the past 20 months, the Huaqin 120 MWp distributed photovoltaic power station has been successfully completed and put into operation.
Based on an average standard coal consumption of 335 g/kWh for thermal power generation, this project can save 101,267.79 tonnes of standard coal annually, reduce particulate matter emissions by 5,442.7 tonnes per year, cut sulfur dioxide emissions by 1,965.43 tonnes per year, and lower carbon dioxide emissions by 289,987.72 tonnes per year—while also conserving substantial water resources. Gazing at the neatly arranged photovoltaic panels and the newly upgraded electrical equipment, every staff member is filled with a profound sense of accomplishment. This marks both an end and a new beginning. We look forward to achieving even greater success in the future!