Blogs Details
A Record of Market Development in Taizhou
Release Date:
2019-11-01
Source:
In May 2019, the New Energy Division officially entered the photovoltaic market in Taizhou City, Zhejiang Province. Entering this new market is fraught with both challenges and opportunities: on the one hand, the Taizhou PV market has already undergone preliminary outreach and screening by various investors, leaving only a limited number of high-quality rooftop resources; on the other hand, operating in a “home-field” environment means unfamiliarity with local government agencies such as the Power Supply Bureau and the Development and Reform Commission, necessitating the re-establishment and strengthening of relationships with these key stakeholders.
However, the New Energy Division has remained undeterred by this challenging market environment and continues to seek high-quality rooftop partners. Leveraging its many years of experience in photovoltaic project development and its ability to respond swiftly throughout the process, the division successfully secured energy management agreements for 0.7 MWp of rooftop PV capacity at Weishite and 0.4 MWp at Hailun by the end of June.
The Weishite project commenced construction in July and was officially connected to the grid at the end of September, successfully meeting the critical “930” deadline for securing the feed-in tariff. As the company’s first distributed photovoltaic project in Taizhou, the Weishite project faced significant challenges due to insufficient local resource support, particularly in terms of grid connection and the grid-connection approval process. Nevertheless, the project team worked in unison to achieve on-time grid connection within the prescribed timeframe, thereby safeguarding the client’s maximum interests and marking the New Energy Business Unit’s successful entry into the Taizhou market—their first step in this region.
The 0.4 MW distributed photovoltaic power generation project for ocean-going vessels in Linhai commenced construction at the project site in late September. Leveraging the experience and valuable local resources accumulated through the Wistart project, the project was successfully connected to the grid and handed over on schedule in mid-October, setting a new record for the shortest construction period!
Wistart 0.7 MW rooftop site